#11362·EHS
White Pigeon Baghouse Expansion
Expand baghouse capacity to support throughput increase.
Central · White Pigeon Site
Adam Daktor PM
Emma Davis Submitter
Aug 8, 2026 Est. completion
Mar 26, 2026 Approval date
15 years Useful life
Approval timeline
- DirectorSarah KimApproved1 month ago
- VP SupplyMike ChenApproved1 month ago
- VP OpsLinda RodriguezApproved1 month ago
- CFOMatt AndersonApproved1 month ago
Total cost$178,000
Spent to date$5,0003% of budget
Forecast remaining$173,000
Annual benefit$92,000
Problem
Current baghouse capacity is limiting planned throughput increase; secondary filter stacks cannot keep up.
Proposed solution
Add 2nd module to baghouse bank. Increases capacity by 40%.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Add 2nd module to baghouse bank. Increases capacity by 40%. | $178,000 | 15 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $115,700 | 11 yrs | — |
Payback & benefit
Simple payback20 months
5-yr NPV$221,529
IRR43.1%
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
4 transactions · $5,000
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Dec 6, 2025 | CPM Roskamp | Vendor down payment / mobilization | $763 |
| Dec 5, 2025 | Bliss Industries | Progress billing | $876 |
| Dec 4, 2025 | California Pellet Mill | Progress billing | $1,059 |
| Dec 3, 2025 | Kuhl Corp | Final invoice | $2,302 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)