#11363·Safety
Youngsville Safety Guarding Upgrade
OSHA compliance upgrade for machine guarding in extrusion area.
East · Youngsville Site
Dan Caron PM
Jesse Bryerton Submitter
Jun 4, 2026 Est. completion
Apr 6, 2026 Approval date
15 years Useful life
Approval timeline
- DirectorSarah KimApproved1 month ago
- VP SupplyMike ChenApproved1 month ago
- VP OpsLinda RodriguezApproved1 month ago
- CFOMatt AndersonApproved1 month ago
Total cost$48,500
Spent to date$2,0004% of budget
Forecast remaining$46,500
Annual benefit$12,125
Problem
Third-party safety audit identified 14 OSHA general duty clause items in extrusion area.
Proposed solution
Install engineered guarding to cover all pinch points and moving parts per OSHA 1910 Subpart O.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Install engineered guarding to cover all pinch points and moving parts per OSHA 1910 Subpart O. | $48,500 | 15 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $31,525 | 11 yrs | — |
Payback & benefit
Simple payback44 months
5-yr NPV$4,156
IRR7.9%
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
4 transactions · $1,549
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Dec 25, 2025 | Bliss Industries | Vendor down payment / mobilization | $368 |
| Dec 24, 2025 | California Pellet Mill | Progress billing | $379 |
| Dec 23, 2025 | Kuhl Corp | Progress billing | $393 |
| Dec 22, 2025 | Grainger Industrial | Progress billing | $409 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)