#11363·Safety

Youngsville Safety Guarding Upgrade

OSHA compliance upgrade for machine guarding in extrusion area.

ApprovedHigh
East · Youngsville Site
Dan Caron PM
Jesse Bryerton Submitter
Jun 4, 2026 Est. completion
Apr 6, 2026 Approval date
15 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
Total cost$48,500
Spent to date$2,0004% of budget
Forecast remaining$46,500
Annual benefit$12,125

Problem

Third-party safety audit identified 14 OSHA general duty clause items in extrusion area.

Proposed solution

Install engineered guarding to cover all pinch points and moving parts per OSHA 1910 Subpart O.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedInstall engineered guarding to cover all pinch points and moving parts per OSHA 1910 Subpart O.$48,50015 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$31,52511 yrs

Payback & benefit

Simple payback44 months
5-yr NPV$4,156
IRR7.9%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

4 transactions · $1,549
DateVendorDescriptionAmount
Dec 25, 2025Bliss IndustriesVendor down payment / mobilization$368
Dec 24, 2025California Pellet MillProgress billing$379
Dec 23, 2025Kuhl CorpProgress billing$393
Dec 22, 2025Grainger IndustrialProgress billing$409

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)

Comments

(0)