#11366·R/M

Arcade Pellet Mill Rotor Rebuild

Scheduled 5-year rotor rebuild on Mill #1.

CompleteMedium
Central · Arcade Site
Adam Daktor PM
Emma Davis Submitter
Est. completion
Aug 23, 2025 Approval date
5 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
Total cost$98,000
Spent to date$98,000100% of budget
Forecast remaining$0
Annual benefit$24,500

Problem

Scheduled 5-year rotor rebuild per maintenance program.

Proposed solution

Send rotor to OEM for rebuild. Install loaner during 2-week downtime.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedSend rotor to OEM for rebuild. Install loaner during 2-week downtime.$98,0005 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$63,7003 yrs

Payback & benefit

Simple payback44 months
5-yr NPV$8,396
IRR7.9%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

8 transactions · $98,000
DateVendorDescriptionAmount
Feb 20, 2026Grainger IndustrialVendor down payment / mobilization$12,863
Feb 19, 2026Motion IndustriesProgress billing$12,892
Feb 18, 2026Applied Industrial TechnologiesProgress billing$12,884
Feb 17, 2026WW GraingerProgress billing$12,822
Feb 16, 2026Kice IndustriesProgress billing$12,682
Feb 15, 2026Peerless MfgProgress billing$12,414
Feb 14, 2026Schenck ProcessProgress billing$11,901
Feb 13, 2026MAC EquipmentFinal invoice$9,542

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)