#11378·Thermal EventUNPLANNED

Jaffrey Thermal Event Response Q1

Initial response and containment from thermal event preceding the broader remediation program (ref #11412).

CompleteCritical
East · Jaffrey Site
Chris LeBarre PM
Ryan Thompson Submitter
Est. completion
Mar 21, 2026 Approval date
5 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
  5. CEOTom Blake
    Approved1 month ago
Total cost$612,000
Spent to date$612,000100% of budget
Forecast remaining$0
Annual benefit

Problem

Immediate containment and temporary operations restoration following March 28 thermal event.

Proposed solution

Emergency contractor mobilization, temporary panel installation, insurance-approved cleanup, and operations restart under limited-capacity permit.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedEmergency contractor mobilization, temporary panel installation, insurance-approved cleanup, and operations restart under limited-capacity permit.$612,0005 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$397,8003 yrs

Payback & benefit

Simple payback
5-yr NPV-$612,000
IRR

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

5 transactions · $612,000
DateVendorDescriptionAmount
Dec 9, 2025WW GraingerVendor down payment / mobilization$107,712
Dec 8, 2025Kice IndustriesProgress billing$112,204
Dec 7, 2025Peerless MfgProgress billing$117,625
Dec 6, 2025Schenck ProcessProgress billing$124,879
Dec 5, 2025MAC EquipmentFinal invoice$149,580

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)