#11381·R/M Unplanned EFUNPLANNED

Hayward Screw Press Shaft Replacement

Replace fractured main drive shaft on Screw Press #1.

ApprovedHigh
West · Hayward Site
Cody Smith PM
Jake Morales Submitter
May 24, 2026 Est. completion
Apr 8, 2026 Approval date
7 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
Total cost$195,000
Spent to date$8,4004% of budget
Forecast remaining$186,600
Annual benefit$48,750

Problem

Hairline fracture detected on main drive shaft during monthly NDT inspection. Stress analysis indicates imminent failure within 6-8 weeks under current load.

Proposed solution

Proactive replacement with upgraded shaft (higher yield strength) during planned maintenance window. Avoids unplanned failure and associated downtime.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedProactive replacement with upgraded shaft (higher yield strength) during planned maintenance window. Avoids unplanned failure and associated downtime.$195,0007 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$126,7503 yrs

Payback & benefit

Simple payback44 months
5-yr NPV$16,708
IRR7.9%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

5 transactions · $8,400
DateVendorDescriptionAmount
Jan 14, 2026Bliss IndustriesVendor down payment / mobilization$1,882
Jan 13, 2026California Pellet MillProgress billing$1,841
Jan 12, 2026Kuhl CorpProgress billing$1,777
Jan 11, 2026Grainger IndustrialProgress billing$1,667
Jan 10, 2026Motion IndustriesFinal invoice$1,233

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)