#11391·R/M

Jaffrey HVAC Upgrade (Administrative)

Replace office HVAC system with high-efficiency unit.

DraftLow
East · Jaffrey Site
Chris LeBarre PM
Ryan Thompson Submitter
Aug 18, 2026 Est. completion
Approval date
18 years Useful life
This request has not been submitted yet.
Total cost$32,000
Spent to date$00% of budget
Forecast remaining$32,000
Annual benefit$8,200

Problem

Existing HVAC is 22 years old; repair costs exceeded $9k in 2025.

Proposed solution

Replace with high-efficiency unit. Includes economizer for shoulder-season savings.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedReplace with high-efficiency unit. Includes economizer for shoulder-season savings.$32,00018 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$20,80014 yrs

Payback & benefit

Simple payback43 months
5-yr NPV$3,610
IRR8.9%