#11393·R/M
MTI Plant Air Filter System
Upgrade plant compressed air filter and dryer system.
MTI · MTI Plant 1 Site
Luc Boisvert PM
Emma Davis Submitter
Jun 4, 2026 Est. completion
Apr 8, 2026 Approval date
12 years Useful life
Approval timeline
- DirectorSarah KimApproved1 month ago
- VP SupplyMike ChenApproved1 month ago
- VP OpsLinda RodriguezApproved1 month ago
- CFOMatt AndersonApproved1 month ago
Total cost$42,500
Spent to date$2,0005% of budget
Forecast remaining$40,500
Annual benefit$16,000
Problem
Current filter/dryer system allows oil carryover into instrument air.
Proposed solution
Install coalescing filter + refrigerated dryer train with ISO 8573-1 Class 2 spec.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Install coalescing filter + refrigerated dryer train with ISO 8573-1 Class 2 spec. | $42,500 | 12 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $27,625 | 8 yrs | — |
Payback & benefit
Simple payback28 months
5-yr NPV$26,983
IRR25.6%
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
7 transactions · $1,746
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Mar 22, 2026 | Grainger Industrial | Vendor down payment / mobilization | $238 |
| Mar 21, 2026 | Motion Industries | Progress billing | $242 |
| Mar 20, 2026 | Applied Industrial Technologies | Progress billing | $246 |
| Mar 19, 2026 | WW Grainger | Progress billing | $250 |
| Mar 18, 2026 | Kice Industries | Progress billing | $253 |
| Mar 17, 2026 | Peerless Mfg | Progress billing | $257 |
| Mar 16, 2026 | Schenck Process | Progress billing | $260 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)