#11395·R/M

Kingwood PLC Controls Modernization

Modernize mill #3 PLC from legacy system to current Allen-Bradley platform.

In ReviewMedium
East · Kingwood Site
Bill Kerstetter PM
Jesse Bryerton Submitter
Aug 8, 2026 Est. completion
Approval date
15 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved7 days ago
  2. VP SupplyMike Chen
    Approved6 days ago
  3. VP OpsLinda Rodriguez
    Pending3 days in queue
  4. CFOMatt Anderson
    Awaiting
Total cost$165,000
Spent to date$00% of budget
Forecast remaining$165,000
Annual benefit$88,000

Problem

Mill #3 PLC is 18 years old, parts are obsolete, and support ends in 2027. Recent spare-parts procurement required a 10-week wait.

Proposed solution

Replace with ControlLogix platform. Includes new HMI, historian integration, and staff training.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedReplace with ControlLogix platform. Includes new HMI, historian integration, and staff training.$165,00015 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$107,25011 yrs

Payback & benefit

Simple payback19 months
5-yr NPV$217,158
IRR45.0%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

0 transactions · $0

No ERP transactions yet.

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)

Comments

(1)
  • BK
    Bill Kerstetter·6 days ago

    Reviewed quote with Allen-Bradley local rep. They'll host training in Kingwood for maintenance team.