#11404·R/M Unplanned EFUNPLANNED

Kingwood Dust Collection System Emergency Replacement

Replace primary dust collection system following baghouse structural failure and combustible dust code violation.

ApprovedCritical
East · Kingwood Site
Bill Kerstetter PM
Jesse Bryerton Submitter
Jul 14, 2026 Est. completion
Apr 15, 2026 Approval date
15 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
  5. CEOTom Blake
    Approved1 month ago
Total cost$356,200
Spent to date$22,0006% of budget
Forecast remaining$334,200
Annual benefit$89,050

Problem

State inspector issued code violation on combustible dust program following baghouse structural inspection. Current system does not meet NFPA 652/654 hazard analysis requirements.

Proposed solution

Install new 10,000 CFM cartridge collector system with deflagration vent, spark detection, and explosion isolation. Compliant with current NFPA standards.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedInstall new 10,000 CFM cartridge collector system with deflagration vent, spark detection, and explosion isolation. Compliant with current NFPA standards.$356,20015 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$231,53011 yrs

Payback & benefit

Simple payback44 months
5-yr NPV$30,518
IRR7.9%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

7 transactions · $22,000
DateVendorDescriptionAmount
Feb 7, 2026Fike CorpVendor down payment / mobilization$2,137
Feb 6, 2026Camfil APCProgress billing$2,284
Feb 5, 2026Andritz Feed & BiofuelProgress billing$2,461
Feb 4, 2026CPM RoskampProgress billing$2,683
Feb 3, 2026Bliss IndustriesProgress billing$2,984
Feb 2, 2026California Pellet MillProgress billing$3,450
Feb 1, 2026Kuhl CorpFinal invoice$6,001

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)

Comments

(0)