#11359·EHS
Mifflintown Baghouse Cleaning System
Pulse-jet cleaning system upgrade on dust collector #2.
East · Mifflintown Site
Dan Caron PM
Ryan Thompson Submitter
— Est. completion
Nov 6, 2025 Approval date
10 years Useful life
Approval timeline
- DirectorSarah KimApproved1 month ago
- VP SupplyMike ChenApproved1 month ago
- VP OpsLinda RodriguezApproved1 month ago
- CFOMatt AndersonApproved1 month ago
Total cost$95,000
Spent to date$95,000100% of budget
Forecast remaining$0
Annual benefit$23,750
Problem
Existing pulse-jet system operating at 78% efficiency (spec: 92%). Contributing to elevated emissions and baghouse pressure drops.
Proposed solution
Install new pulse-jet controller with individual valve sequencing. Improves cleaning efficiency and extends bag life by an estimated 40%.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Install new pulse-jet controller with individual valve sequencing. Improves cleaning efficiency and extends bag life by an estimated 40%. | $95,000 | 10 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $61,750 | 6 yrs | — |
Payback & benefit
Simple payback44 months
5-yr NPV$8,140
IRR7.9%
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
4 transactions · $95,000
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Mar 20, 2026 | Applied Industrial Technologies | Vendor down payment / mobilization | $27,788 |
| Mar 19, 2026 | WW Grainger | Progress billing | $26,437 |
| Mar 18, 2026 | Kice Industries | Progress billing | $24,261 |
| Mar 17, 2026 | Peerless Mfg | Final invoice | $16,514 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)