#11368·R/M
White Pigeon Warehouse Racking + Loader Pool
Multi-level pallet racking in finished-goods warehouse plus additional forklift pool.
Central · White Pigeon Site
Adam Daktor PM
Emma Davis Submitter
Aug 8, 2026 Est. completion
Mar 29, 2026 Approval date
20 years Useful life
Approval timeline
- DirectorSarah KimApproved1 month ago
- VP SupplyMike ChenApproved1 month ago
- VP OpsLinda RodriguezApproved1 month ago
- CFOMatt AndersonApproved1 month ago
- CEOTom BlakeApproved1 month ago
Total cost$320,000
Spent to date$22,0007% of budget
Forecast remaining$298,000
Annual benefit$180,000
Problem
Warehouse is at capacity during peak season; current racking limits pallet-high storage to 2 levels.
Proposed solution
Multi-level pallet racking for 4 levels + 2 additional battery-electric reach trucks.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Multi-level pallet racking for 4 levels + 2 additional battery-electric reach trucks. | $320,000 | 20 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $208,000 | 16 yrs | — |
Payback & benefit
Simple payback18 months
5-yr NPV$461,688
IRR48.4%
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
4 transactions · $22,000
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Mar 30, 2026 | Applied Industrial Technologies | Vendor down payment / mobilization | $4,785 |
| Mar 29, 2026 | WW Grainger | Progress billing | $5,050 |
| Mar 28, 2026 | Kice Industries | Progress billing | $5,413 |
| Mar 27, 2026 | Peerless Mfg | Final invoice | $6,752 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)