#11385 · Mifflintown · PM Dan Caron
Forecast — Mifflintown Rotor Refurbishment
Next auto-reminder: May 1
Total cost $267,000 · Spent $145,000 · Forecast remaining $122,000
| Month | Forecast | Actual (ERP) | Variance |
|---|---|---|---|
| Jan 26 | $51,241 | $2,908 | |
| Feb 26 | $43,835 | -$4,498 | |
| Mar 26 | $46,996 | -$1,337 | |
| Apr 26 | $6,778 | -$5,422 | |
| May 26 | — | — | |
| Jun 26 | — | — | |
| Jul 26 | — | — | |
| Aug 26 | — | — | |
| Sep 26 | — | — | |
| Oct 26 | — | — | |
| Nov 26 | — | — | |
| Dec 26 | — | — | |
| Total | $265,647 | $148,850 |
Changes auto-save on blur.
Change history
(0)No changes logged yet. Edits to the forecast above will appear here.
Email log