#11399·R/M Unplanned EFUNPLANNED

Youngsville Bearing Cascade Failure

Cascade bearing failure in main mill drivetrain. Required full drivetrain assessment and sequential component replacement.

In ProgressCritical
East · Youngsville Site
Dan Caron PM
Jesse Bryerton Submitter
May 15, 2026 Est. completion
Mar 9, 2026 Approval date
10 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
  5. CEOTom Blake
    Approved1 month ago
Total cost$572,800
Spent to date$310,00054% of budget
Forecast remaining$262,800
Annual benefit$143,200

Problem

Sequential bearing failures in the main mill drivetrain over 14 days cascaded into gearbox damage. Root cause: lubrication system cross-contamination from a failed filter.

Proposed solution

Replace all affected bearings, rebuild gearbox, install upgraded filtration system with differential pressure monitoring, and retrain maintenance team on new lube program.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedReplace all affected bearings, rebuild gearbox, install upgraded filtration system with differential pressure monitoring, and retrain maintenance team on new lube program.$572,80010 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$372,3206 yrs

Payback & benefit

Simple payback44 months
5-yr NPV$49,076
IRR7.9%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

8 transactions · $310,000
DateVendorDescriptionAmount
Feb 24, 2026Schenck ProcessVendor down payment / mobilization$46,888
Feb 23, 2026MAC EquipmentProgress billing$45,857
Feb 22, 2026Fike CorpProgress billing$44,537
Feb 21, 2026Camfil APCProgress billing$42,834
Feb 20, 2026Andritz Feed & BiofuelProgress billing$40,589
Feb 19, 2026CPM RoskampProgress billing$37,504
Feb 18, 2026Bliss IndustriesProgress billing$32,887
Feb 17, 2026California Pellet MillFinal invoice$18,904

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)