#11411·EHS

Coppercoin Wastewater System Upgrade

Upgrade wastewater treatment capacity and add polymer injection.

ApprovedHigh
Central · Coppercoin Site
Adam Daktor PM
Emma Davis Submitter
Oct 17, 2026 Est. completion
Apr 10, 2026 Approval date
20 years Useful life

Approval timeline

  1. DirectorSarah Kim
    Approved1 month ago
  2. VP SupplyMike Chen
    Approved1 month ago
  3. VP OpsLinda Rodriguez
    Approved1 month ago
  4. CFOMatt Anderson
    Approved1 month ago
  5. CEOTom Blake
    Approved1 month ago
Total cost$318,000
Spent to date$8,0003% of budget
Forecast remaining$310,000
Annual benefit$72,000

Problem

Discharge permit tightening requires improved phosphorus removal by 2027.

Proposed solution

Upgrade DAF unit, add polymer injection, install online phosphorus analyzer.

Justification

No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.

Alternatives

OptionDescriptionTotal costUseful lifeRecommended
Option 1 — RecommendedUpgrade DAF unit, add polymer injection, install online phosphorus analyzer.$318,00020 yrs
Option 2 — Rebuild in placeRebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing.$206,70016 yrs

Payback & benefit

Simple payback49 months
5-yr NPV-$5,325
IRR4.3%

Actuals (from ERP)

Sourced from the financial system integration. Last sync 2 hours ago.

5 transactions · $8,000
DateVendorDescriptionAmount
Jan 10, 2026Schenck ProcessVendor down payment / mobilization$2,176
Jan 9, 2026MAC EquipmentProgress billing$1,995
Jan 8, 2026Fike CorpProgress billing$1,761
Jan 7, 2026Camfil APCProgress billing$1,437
Jan 6, 2026Andritz Feed & BiofuelFinal invoice$631

Attachments

  • vendor-quote.pdf(245 KB)
  • site-photo.jpg(1820 KB)