East Region Thermal Event Remediation
Remediation following thermal event in Jaffrey dryer system. Includes dryer panel replacement, wiring harness, fire suppression upgrade, and safety audit response.
Approval timeline
- DirectorSarah KimApproved10 days ago
“Critical safety response. Approved.”
- VP SupplyMike ChenApproved9 days ago
“Vendor engagement confirmed. Approved.”
- VP OpsLinda RodriguezApproved7 days ago
“Reviewed scope. Approved.”
- CFOMatt AndersonApproved3 days ago
“Budget accommodation confirmed. Approved.”
- CEOTom BlakePending3 days in queue
Problem
Thermal event in Jaffrey Dryer #2 on March 28 resulted in fire-suppression activation, partial panel melt, and 6 days of lost production before temporary containment. Insurance-documented damages total $210k; additional $70k required for fire-code remediation per state fire marshal inspection.
Proposed solution
Replace Dryer #2 center panel assembly and wiring harness (OEM), upgrade fire suppression system to meet revised NFPA 654 requirements, engage third-party audit for combustible dust program, and complete state fire marshal re-inspection before restart.
Justification
No justification drafted yet. Click “Draft with AI” to generate one from the problem & solution fields.
Alternatives
| Option | Description | Total cost | Useful life | Recommended |
|---|---|---|---|---|
| Option 1 — Recommended | Replace Dryer #2 center panel assembly and wiring harness (OEM), upgrade fire suppression system to meet revised NFPA 654 requirements, engage third-party audit for combustible dus | $282,500 | 12 yrs | ✓ |
| Option 2 — Rebuild in place | Rebuild existing equipment in place with refurbished components. Lower upfront cost but shorter useful life and higher maintenance ongoing. | $183,625 | 8 yrs | — |
Payback & benefit
Actuals (from ERP)
Sourced from the financial system integration. Last sync 2 hours ago.
| Date | Vendor | Description | Amount |
|---|---|---|---|
| Jan 29, 2026 | MAC Equipment | Vendor down payment / mobilization | $6,989 |
| Jan 28, 2026 | Fike Corp | Progress billing | $7,253 |
| Jan 27, 2026 | Camfil APC | Progress billing | $7,556 |
| Jan 26, 2026 | Andritz Feed & Biofuel | Progress billing | $7,921 |
| Jan 25, 2026 | CPM Roskamp | Progress billing | $8,409 |
| Jan 24, 2026 | Bliss Industries | Final invoice | $10,072 |
Attachments
- vendor-quote.pdf(245 KB)
- site-photo.jpg(1820 KB)
Comments
(2)- CLChris LeBarre·2 days ago
Insurance adjuster has signed off on scope. Awaiting final approval to release long-lead-time items.
- RTRyan Thompson·5 days ago
State fire marshal inspection scheduled for April 30. Need the remediation scope finalized by April 25 to hit that date.